- Building Permit Application
- $150
- Time extension (maximum one extension)
- $150
- For construction, addition, alteration, repair, removal or demolition of a structure or part thereof:
- 1.2% of actual construction value of project + surcharge of:
- where the construction value is less than $10,000
- $50 surcharge
- where the construction value is $10,000 - $22,000
- $100 surcharge
- where the construction value is in excess of $22,000
- $200 surcharge
- Where a project includes plumbing, an additional fee per plumbing fixture applies, i.e. trap, roof drain, floor drain, yard or parking lot drain
- $10 per fixture count per fixture count
- Placing a manufactured dwelling (CSA Z240, CSA A277) on a property, or relocating dwelling to a property.
- $400 + 1.2% of the construction cost of those